DNO boosts Kurdistan’s Peshkabir oil production to 50,000 bpd ahead of schedule

Norwegian oil and gas operator DNO on Monday announced output at the Peshkabir (Faysh Khabur) field in the Kurdistan Region of Iraq has ramped up to 50,000 barrels of oil per day (bpd), meeting the end-2018 target ahead of schedule and below budget.

ERBIL (Kurdistan 24) – Norwegian oil and gas operator DNO on Monday announced output at the Peshkabir field in the Kurdistan Region of Iraq has ramped up to 50,000 barrels of oil per day (bpd), meeting the end-2018 target ahead of schedule and below budget.

One of two recently completed wells, Peshkabir-7, is producing over 10,000 bpd from nine Cretaceous zones through temporary test facilities and exported. The other, Peshkabir-6, drilled as a production well but with the additional objective of appraising deeper formations, has established a deeper Cretaceous oil/water contact level than previously estimated, DNO said in a statement.

Further testing is underway, including test production of multiple producing zones.

The company mentioned that the Peshkabir-8 well, spud in late August, is drilling ahead at 2,325 meters. Once completed, the rig will move to spud Peshkabir-9 in November.

Four other wells at Peshkabir now produce at a combined rate of close to 40,000 bpd, following a workover at Peshkabir-3 which boosted production from that well to 11,000 bpd from 8,000 bpd.

Peshkabir production is processed through temporary test facilities until the commissioning of a central processing facility with a capacity of up to 50,000 bpd by end-2018, DNO stated.

The company is also installing a 10-inch pipeline from Peshkabir to connect with the Kurdistan Region’s main oil pipeline to Turkey, with a capacity of 60,000 bpd. Field production is currently transported to the border area of Faysh Khabur by tanker truck and a 6-inch pipeline.

At the company’s flagship Tawke field, the Tawke-50 shallow Jeribe Well drilled to a depth of 320 meters will be brought into production within several days.

The Tawke-49 Cretaceous well is drilling ahead at 2,245 meters and will be completed later this month. Two additional Tawke wells, one each in the Jeribe and the Cretaceous, will be drilled by the end of the year. Workovers are also underway at two wells. 

The Tawke production currently stands at just over 80,000 bpd.

Elsewhere in Kurdistan, DNO is about to spud its first well at the Bashiqa license. Bashiqa contains two undrilled structures with multiple target reservoirs in the Cretaceous, Jurassic, and Triassic.

The first well will target the Cretaceous and will be followed by a back-to-back well to test the deeper Jurassic and Triassic on the same structure. A third well to test the Jurassic and Triassic on a separate structure will be drilled in 2019.

“We are all in on our Kurdistan operations and delivering,” said DNO’s Executive Chairman Bijan Mossavar-Rahmani in a statement published on Monday. “Peshkabir continues to exceed expectations, and we are eager to probe the promising potential at Bashiqa.”

“With USD 1 billion in financial assets, including more than USD 600 million in cash and the balance in marketable securities and treasury shares, we are well-positioned to grow our footprint in Kurdistan and Norway with the drill bit and the acquisition of producing assets,” said Mossavar-Rahmani.

Editing by Nadia Riva